This panel displays the manufacturing or purchase orders that are proposed to be re-scheduled or deleted. The orders are automatically marked for re-scheduling or deletion by the system in the following cases:
- Backward re-scheduling
Backward re-scheduling of manufacturing or purchase orders is done by manually changing the Planned compl date or the Disp date to an earlier date. See Re-schedule an order created from an MRP order proposal for instructions. - Forward re-scheduling
Forward re-scheduling of manufacturing or purchase orders is done by manually changing the Planned compl date or the Disp date to a later date. See Re-schedule an order created from an MRP order proposal for instructions. - Deletion
Deletion is proposed by the system if there is no matching proposal for a manufacturing/purchase order. This can be the case if a reservation is deleted. Note: Deletion of manufacturing orders or purchase orders is done via the Work with manufacturing orders and Work with purchase orders menu items.
If you do not wish to re-schedule or delete an order you can omit the re-scheduling. This means that the manufacturing or purchase order is accepted without changes, and that re-scheduling never again will be proposed for the order. See Omit an MRP re-schedule order proposal for instructions.
Options
| Maintain order | Select this option to maintain the manufacturing or purchase order header. Re-scheduling is done by manually changing the manufacturing order’s Planned compl date or the purchase order’s Disp date. |
| Order overview | Select this option to maintain the manufacturing or purchase order lines. |
| Omit re-schedule | Select this option to omit the re-schedule proposal for a manufacturing or purchase order. Once this option has been used, re-scheduling will never again be proposed for the order. |
Function keys
| MRP pegging | View the origin of the order proposal. A reference is attached to the calculated requirement entries, pointing at the closest non-phantom item one level up in the item structure causing the requirement. |
- Item
- Warehouse
- Unit
- EOQ
- The economic order quantity.
- Safety stock
- The safety stock quantity.
- On hand
- The quantity on hand at the creation time for the proposal.
- Cost price
- The cost price of the item.
- Req date
- The requirement date.
- Type
- Indicates if the order number refers to a manufacturing order or a purchase order.
- Order number
- The order number of the manufacturing or purchase order.
- Start date
- For purchase orders this field is blank.
- Quantity
- A
- The action code indicates the type of re-scheduling that is proposed by the system.
Code Type Action 1 Backward re-scheduling Manually change the Planned compl date or the Disp date to an earlier date on the order header. 2 Forward re-scheduling Manually change the Planned compl date or the Disp date to a later date on the order header. 3 Deletion Delete the manufacturing or purchase order manually via the Work with manufacturing orders and Work with purchase orders menu items.
- C
- Indicates if the order has been changed after the creation of the MRP proposal.
- New rq date
- The new requirement date according to the action code.
- Supplier
- This field is only displayed if the item type is 3 (material) or 4 (purchased). The supplier for the purchase order.